Renovation of Primrose house update April 11, 2016:

Inspection was conducted on Wednesday, 6th April 2016. Please see brief description of progress below:
·         The windows have been completed except the installation of mosquito nets.
·         Additional ceiling fans need to be installed for an additional cost of N 56,000.
·         Ceiling leaks were identified in the dorm. The leak will cost an additional N60,000 to repair.
·         Painting and Flooring will occur in the upcoming weeks.
·         The Contractor noticed severe rusting of the hostel gates. This was not priced initially. If we choose to replace the gates, it will be an additional N240,000. If we mend the gates, cost will be N15,000
In summary - we are looking at additional N131K or N356K if we decide to replace the dorm gates. 2nd inspection will be on Friday, 15th April 2016 at 10am.
PLEASE, your donation is of utmost importance to ensure completion on our class project. Thank you all for your generosity.